Bipartisan Permitting Reform Proposal: BAAJA Overview and Analysis
Executive Summary
- The Senate is likely to soon vote on the Bipartisan American Affordability and Jobs Act of 2026 (BAAJA), which would significantly accelerate energy infrastructure permitting and review processes; the proposal covers a lot of ground as it has to harness support from both Democratic and Republican lawmakers.
- The decades-old, overlapping federal permitting processes are slow, inefficient, and tedious, with mandatory environmental assessments taking on average 54 months across all project types, and transmission lines taking on average 10 years to complete.
- This insight provides an overview of BAAJA and analyzes its impact on the grid, energy markets, and data centers; it concludes that the legislation would help to reduce regulatory barriers, accelerate energy infrastructure development, and ensure the grid can meet rising energy and economic growth demand.
Introduction
The Bipartisan American Affordability and Jobs Act of 2026 (BAAJA) – introduced on September 30, 2026, by Senators Shelley Moore Capito (R-WV), Mike Lee (R-UT), Sheldon Whitehouse (D-RI), and Martin Heinrich (D-NM) – would significantly accelerate permitting and energy infrastructure review processes. The Senate is expected to move forward with a final vote on the bill before the Thanksgiving recess.
The decades-old, overlapping federal permitting processes are slow, inefficient, and tedious, with environmental assessments taking on average 54 months across all project types. Even after review is completed, decisions may still be litigated in court for up to six years afterward. Over the past two decades, transmission lines that transfer electricity from power plants to consumers took on average 10 years to complete, with some taking 15 years or longer.
This insight provides an overview of BAAJA’s key provisions, and considers its potential impact on the grid, energy markets, and data centers. It concludes that the legislation would help reduce regulatory barriers, accelerate energy infrastructure development, and ensure the grid can meet rising energy and economic growth demand.
The Urgent Need for Permitting Reform in the United States
When a U.S. developer plans to build any type of infrastructure (e.g., a road, bridge, solar farm, or natural gas pipeline), it would need to comply with permitting regulations at the federal, state, and local level to obtain required permits before the project can start. Decades-old and overlapping federal processes implemented by multiple government agencies have made the current permitting processes inefficient, slow, and tedious. For example, the National Environmental Policy Act (NEPA), the major U.S. federal permitting law enacted in 1970, mandates assessments on the environmental effects of infrastructure projects, which on average take about 54 months across all project types. Even after the review is completed, the decisions may still be challenged in court for up to six years afterward.
Permitting reform is also crucial for meeting surging U.S. electricity demand, primarily driven by artificial intelligence (AI) data centers, domestic manufacturing, and electrification of different sectors. Over the past two decades, transmission lines that transfer electricity from power plants to consumers took on average 10 years to complete, with some taking 15 years or longer. The average time from submission of a power plant grid connection request to commercial operation rose from under two years in 2008 to nearly five in 2023.
The United States is extremely unlikely to achieve necessary buildout of infrastructure on the timeline required to meet growing energy and economic demand without significant reform of the federal permitting process.
Permitting reform broadly has been under discussion in Congress for some years, and numerous bills have been introduced. It is rare for any proposal to garner support from key committee leaders, both Republican and Democrat. The Senate is expected to move forward with a final vote on the legislative proposal as soon as later this week. With President Trump’s endorsement, and two strong Senate cloture votes on advancing the bill, and a broad coalition of support from renewable energy trade associations to fossil fuel groups, BAAJA has gained substantial momentum.
The bill has also faced opposition from some Democratic lawmakers who want to revisit the work on permitting reform in the next Congress. Some lawmakers’ concerns about the bill’s sections on tribal sovereignty remain a major sticking point. Several current House Republicans, meanwhile, have reservations about giving the federal government a larger role in transmission planning. If BAAJA is not approved by the House and Senate and signed into law, the effort to reform this regulatory regime will start again in the next Congress. Moreover, it is not clear that incoming congressional leaders would pursue the types of reforms included in BAAJA.
Overview of BAAJA
BAAJA would significantly change permitting and energy infrastructure review processes. It includes proposed changes across several main areas, including transmission and electric grid planning, NEPA, existing environmental regulations, and large load interconnection.
Transmission and electric grid planning
Currently, state and local governments have the authority to approve or deny transmission line projects. The Federal Energy Regulatory Commission (FERC), an independent federal agency, has limited authority to approve interstate transmission projects located in national interest electric transmission corridors designated by the Department of Energy.
The legislation would refine and expand the federal backstop siting authority, allowing FERC to intervene if states delay or block interstate transmission lines. This would reduce project bottlenecks and streamline the permitting process for construction of transmission lines across multiple states.
Changes to the National Environmental Policy Act
BAAJA would reduce the review timeline under NEPA. For example, it would expand the categorical exemptions—certain activities deemed not to have a significant environmental impact and therefore exempt from NEPA review—which would reduce the total number of energy projects requiring such review. It would also establish stricter environmental review deadlines and hold accountable government agencies that miss the deadlines. The bill would also require most NEPA-tied legal challenges initiated against energy projects be filed within 150 days of final project approval, preventing years-long permitting litigation that sometimes occurs under current law.
Revising other environmental regulations
The bill would also change other federal regulations applicable to permitting of infrastructure projects.
The Clean Water Act (CWA), for example, regulates water pollution. Section 401 of the CWA grants a state or certain authorized tribes the authority to block projects that cause direct water pollution. The bill would narrow that authority, preventing its use to block projects for reasons other than water pollution, including potential impacts on air quality, endangered species, or noise.
The bill would also amend Section 106 of the National Historic Preservation Act (NHPA), which requires federal agencies to consider and prevent harms to historic properties caused by permitted infrastructure projects. Since Section 106 does not set any time limit for the review process, and local preservation offices often lack sufficient staff, it can take years for some proposals to complete the review process. This particularly affects transmission lines and energy pipelines that cross several jurisdictions. BAAJA would significantly narrow the scope of Section 106 and set strict deadlines for the review.
The bill’s proposed changes to Section 106 of the NHPA have drawn strong opposition from tribal nations that argue BAAJA would infringe upon legal protection of historic sites and tribal sovereignty. On November 7, 2026, a manager’s amendment was introduced to address some of these concerns. The amendment removed a provision that would have allowed the federal government to define which properties qualify as culturally important, instead preserving the existing process for tribal input. Tribal organizations continue to oppose BAAJA, however, arguing the proposed revisions would “continue to fundamentally undermine Tribal sovereignty, weaken longstanding federal protections, fail to ensure meaningful government-to-government Tribal consultation, and threaten sacred sites and cultural resources.”
Large load interconnection
From 2024–2030, data centers are estimated to account for 33 percent of projected electricity demand growth. To accommodate the growing demand and prevent residential consumers from bearing the costs of more electricity generation, transmission, and distribution, BAAJA would require data centers that demand 20 megawatts or more to pay for the incremental infrastructure costs associated with their consumption. It would also expand state flexibility to set higher rates for data centers.
The Energy Information Administration (EIA) does not as of now separately track data centers’ electricity consumption, making it hard for utilities and regulators to plan for future demand. BAAJA would require the EIA to report data centers’ electricity consumption.
Impact of BAAJA
Several independent research institutions find that BAAJA would lower electricity costs, expand grid capacity, and support new energy generation. The extent of such benefits, nevertheless, depends on how the bill is implemented.
Impact on permitting timelines
BAAJA would significantly shorten the federal permitting timelines. Columbia University’s Center on Global Energy Policy estimated that if federal agencies comply with BAAJA’s legal review deadlines, permitting timelines would be shortened to 2.5 months for transmission, 5.5 months for solar, less than a month for geothermal, 7 months for offshore wind, 4 months for gas pipelines, and 4.5 months for onshore wind. If federal agencies cannot meet the deadlines and extensions or litigations are triggered, it would be 96 months for transmission, 35 months for solar, 29 months for geothermal, 24 months for offshore wind, 21 months for gas pipelines, and 20 months for onshore wind. Additionally, the Natural Resources Defense Council estimated that the bill’s transmission provisions would shorten the construction timeline from 10 years to five to six years.
Grid and energy markets impact
BAAJA would reduce electricity costs for households by making it easier to build and connect new power plants to the grid. Rhodium Group, an independent research and data analytics provider, projected that the bill would create annual savings of $50 to $78 in the average household electricity bill in 2040. BAAJA’s transmission provisions would generate hundreds of billions of dollars in energy cost savings by 2050 if implemented effectively, according to the Lighthouse Energy Institute. The main uncertainty is whether the cost allocation provision—which determines how to allocate electricity transmission costs among ratepayers—would result in a net loss or benefit.
BAAJA is also projected to significantly expand the U.S. transmission grid, allowing more electricity to move between regions to meet consumer demand. Resources for the Future estimated total U.S. transmission capacity would be 30 percent higher by 2041 if BAAJA becomes law and is implemented, with inter-regional electricity transferring capacity more than doubling. The Rhodium Group estimated that additional interregional transmission capacity will increase by 167–262 percent through 2040, compared with the status quo.
Data centers’ impact
The Rhodium Group estimated that the bill’s ratepayer protection provisions would increase the rates data centers pay for electricity by 88–102 percent. The Grid Strategies research firm estimated that BAAJA’s ratepayer protection could add $35 billion in transmission charges and $136 billion in generation costs for data centers over 10 years.
Looking Forward
Modernizing U.S. permitting regulations is vital to meeting the country’s growing infrastructure demand. This is a critical moment for lawmakers to pass long overdue meaningful permitting reform to overhaul the current slow and inefficient permitting processes, remove regulatory barriers, accelerate energy infrastructure development, and ensure the grid can meet rising energy and economic growth demand. Failing to pass BAAJA will leave the United States with the existing permitting regulations that undermine the country’s energy and economic security.